MIDDLE EAST WATERS LTD. شركة مياه الشرق الاوسط للمقاولات العامة المحدودة بغداد- العراق
MIDDLE EAST WATERS LTD. شركة مياه الشرق الاوسط للمقاولات العامة المحدودةبغداد- العراق

PROJECTS IMPLEMENTED

  

No

Project Name

Client

Location

Date



Project Description              

 

28 Drain 22 Pumping Station

Ministry of Water Resources

   Babel 2007/2008 Construction of a new pumping station near Musaib city . Work included the construction of concrete water intake and concrete base platform according, installation of eight 75kw vertical axial flow SIGMA pumps with 600mm delivery pipes and all related electrical controls and instrumentations

27

MANDLI 1 Pumping Station

Ministry of Water Resources

Diyala

2006/2007

Installation, test, operation and commissioning of five 650 KW, 6.6 KV vertical pumps with all related mechanical and electrical equipment.

26

NAHRWAN Potable Water Systems

Ministry of Municipality and Labor

Baghdad

2005

Design, supply and installed new water distribution network, including water main feeders, laterals and house connections

25

AL-KEFEL new potable Water Distribution System

Ministry of Municipality and Labor

Babil

2005

Design, supply and installed new water distribution network, including water main feeders, laterals and house connections

24

Rehabilitation of Jissir and Abu Graib sewerage

International Committee of The Red Cross

Baghdad

2004

Work included cleaning and unplugging main sewers, installation of new lifting pumps

23

Supply of utility trucks

Municipility of Romadi

Iraq

2004

Contracts included the supply of a Sewage Vacuum Truck, 5,000 gallons capacity,

Septic vacuum trucks 4000 gallons and water tank trucks 15000 gallons

22

Manufacturing of kiosk substations

Takaful Co./ Baghdad

Baghdad

2004

Manufacturing and supplying of 28 Nos. of 11/0.4 KV  1000/1600 KVA Kiosk substations

21

Rehabilitation of Madan Water Treatment Plant 5300m3/hr

International Committee of The Red Cross

Madan

2003/

2004

The work included the rehabilitation of Chemical equipment, sedimentation tanks, scrapers, sand filters and pumping stations at low lift and high-lift

 

20

Rehabilitation Of Madan Boosting station 24000m3/day

International Committee of The Red Cross

Madan

2004

. Work included supply and laying of ductile piping, engaging the  boosting station with the existing network for the city and rehabilitation of storage tanks

19

Rehabilitation Of Jissir Water Boosting Station 1200m3/hr

International Committee of The Red Cross

Baghdad

2003

Work included erecting new pumps, cleaning storage tanks, renovating the chlorination system, and modifying main 600mm ductile lines.

 

18

Manufacturing of kiosk substations

TikretUniversity

Tikrit

2002

2003

Manufacturing and installing 23 Nos. of 11/0.4 KVA 630/1000 KVA Kiosk substations

 

No

Project Name

Client

Location

Date

 

Project Description

 

17

Erecting new pumps production line

NAJD Pump Manufacturing Establishment

Sult/ Jordan

2002

Work included designing, selecting equipment , erecting and operating mechanical manufacturing procedures for process pump production .

16

Construction of DIJLA Group Complex

Dijla Group

Baghdad

2002

Work included design and implementation of Hydro utility work for 60 apartment and office buildings plus emergency power supply system

15

Construction of AL-Bazoon Water Treatment Plant  1200m3/day

International Committee of The Red Cross

Mission

2000-2001

A turnkey project, The work included the Supply of all materials, construction, erection and commissioning of civil constructions, piping, steel structures, water tanks, concrete filters, electrical power supply, pumps erection, installation of chlorination units, pressurized sand filters and connecting to main city lines.

14

Construction Water System for Hilla General Hospital

International Committee of The Red Cross

, Babylon

2001

Work included the Supply and erect a water pumping station, ground concrete tank, and elevated circular concrete tank, plus the design, construction and erection of an underground wastewater pumping station.

13

Design and construction of Karama Teaching Hospital Waste Water Systems.

International Committee of The Red Cross

Baghdad

2000-2001

Work included Supplying and erecting water pumping station, meter Ground concrete tank, and elevated pressed steel tank, plus the design, construction and erection of an underground wastewater pumping station.

No

Project Name

Client

Location

Date

 

Project Description

 

12

Baji power station

ANSALDO Italy

Baiji Power plant

1999

Location Baji power station at Baji 225 km north of Baghdad

Subcontract to rehabilitate the local instrumentation for turbine house and boiler for units five and unit 6, 220 MW each.

 

11

Dora power station

University of Technology

Dora -Baghdad

2000

Subcontract to rehabilitate the local instrumentation for turbine house and boiler for units 3,4,5,6, 160 MW each

10

Main power supply for KUT emergency hospital.

Premier Urgence Aid Humanitarian

Kut

2000

Design of main 2000 Amp electrical power boards and    emergency power supply and generators

9

Firefighting system for Assass Transmitters site

Ministry Of Industry.

Abu Ghraib

1999

Supply and Install the fire fighting system for the fuel tanks, including pumps, boosters, piping, control and instrumentation.

 

8

Design of Fire fighting system for Baghdad Cigarette factory

Ministry Of Industry.

Baghdad

1997

 

Supply and Install the fire fighting system, water tanks, pumps, boosters, piping, control and instrumentation.

 

7

Rehabilitation of Water storage for AL-Kindi hospital

Premier Urgance Aid Humanitarian

Baghdad

1998

Supply and install two 400 cubic meter pressed steel water tanks with Epoxy treatment

6

Rehabilitation of steam boilers Zahrawi General Hospital

Premier Urgance Aid Humanitarian

Mousel

1998

Complete renovation of main two 5 Ton, 10 bar steam boilers including all utility equipment, softeners, pr-heating tanks and electrical control boards

.

No

Project Name

Client

Location

Date

 

Project Description

 

5

Rehabilitation 28 Nissan complex

water system

United Nations

( UNHCS )

Baghdad

2000

Supply and erect new pumps, design new automatic control panels and renovate and recalibrating pressurized boosting systems.

4

Electromechanical rehabilitation work for ALKINDI General Hospital

Ministry Of Health

Baghdad

1999 2000.

Implementation of new leading electrical supply network.

Erection of heat exchangers with sensors and controls

Supply and erection of a new internal telephone communication network.

3

Design and Implementation of Pressurized Water Boosting Systems for KINDIGeneralHospital

Premier Urgance Aid Humanitarian

Baghdad

1997-1998

Supply erecting and commissioning for two pressurized water boosting systems after a complete study for primary water city sources, available water storage capacity, Hospital water demand and emergency electrical power supply to maintain water supply in all working conditions.

2

Design and operate a hydraulic test station

AL-Shams Co.

Baghdad

1995

Complete test bench for process pumps hydraulic performance test and calibration per BS standards and engineering codes meeting best operation point for customers process application.

1

Design and manufacturing of low-speed mixers for the Tikret Water Treatment plant

Ministry Of Industry

Tikrit

1993

Manufacture and erect main low-speed mixers 2000mm diameter, 40 kw for sedimentation tanks of Plant

 

 

Business Partners

Sigmainvest Engineering

Czech Republic

 

 

 

Dar Alraeen for commercial agencies
 Baghdad-Iraq

 

Caprari pumps

Modena-Italy

 

What's New

Extended business hours

To accomodate our customers' busy schedules, we have extended our hours and are now open later.

 



Print | Sitemap
© Waterton Logistics Management Ltd.